Project Limits: Approximately 1-mile stretch of Wayne Road between Van Born Road to Smith Road.

Project Description: Sidewalk installation on the east side of the road between Van Born and Ecorse and sidewalk on the west side of the road between Ecorse and Smith.

Traffic Impact/Detour: Traffic will be maintained throughout the project with closures at intersections during the pouring of concrete for the new walk. Traffic will be maintained utilizing flaggers.

Schedule: This project will begin in September 2024.

PROJECT UPDATE:

Additional notifications will be provided to those within the project limits throughout the construction process as necessary